Progress report on biggest public works project in Portland history

Think Out Loud

Progress report on biggest public works project in Portland history

Clean

Published on Oct 23, 2026, 1:09:17 PM
Total time: 00:21:20

Episode Description

A million people in the Portland area get their water from the Bull Run watershed, about 25 miles east of the city.

The city council voted in 2017 to build the water filtration plant to protect against cryptosporidium to comply with Environmental Protection Agency standards.

 

The project was originally estimated at $500 million, but since then it’s risen to $2.58 billion. The water bureau says a number of factors worked to drive up the price tag, including skyrocketing construction costs and defending the project against a number of land use challenges. The filtration plant is now the largest public works project in the city’s history.

 

It was originally scheduled to be completed next year. But after delays, it is now about 40% complete and on track to be operational in 2029. The Portland Water Bureau's Interim Chief Engineer Muriel Gueissaz-Teufe joins us, along with Lyda Hakes, the Bull Run supply and treatment manager. They share more details about why this kind of filtration is needed, how it will work and the benefits for Portland area residents.

 